Financial Services·Toronto — 151 Front Street

Fintech Platform (anonymized)

Challenge

A payments processor needed to migrate 24 racks from a legacy Toronto facility to a Tier III site with zero customer-visible downtime, on a 48-hour weekend window.

Solution

StackTrue ran a two-month planning cycle: physical and logical audit, staged cross-connects, pre-cabled destination racks, and a rehearsed cutover runbook. Two CDCE-certified engineers on-site at both facilities during the window, with a live vendor bridge.

Outcome

Cutover completed in 41 hours against a 48-hour budget. Zero customer-visible downtime. Signed chain-of-custody on every asset; Fluke certification on all new cabling.

24
Racks migrated
41 hrs
Cutover time
0 min
Customer downtime
B2B Software·Vancouver — Cologix VAN2

SaaS Company (anonymized)

Challenge

Production database cluster went offline on a Saturday night after a PSU failure cascaded across an A/B feed misconfiguration. Customer-facing outage in progress.

Solution

Engineer on-site within 90 minutes of the P1 page. Diagnosed the PSU cascade, replaced two units from our on-site spares kit, rebalanced the phase load, and validated with the customer's SRE team over bridge.

Outcome

Service restored in 2 hours 20 minutes end-to-end. Written post-mortem delivered within 24 hours, with three configuration recommendations to prevent recurrence.

90 min
Response time
2h 20m
Time to restore
None
Recurrence
Government·Ottawa

Public Sector Client (anonymized)

Challenge

Buildout of 12 new racks in a secure Ottawa facility for a federal workload, requiring TIA-942 compliance, cleared personnel, and audit-ready documentation for every step.

Solution

StackTrue delivered turn-key rack & stack with cleared engineers on-site. Full labeling to TIA-606, MPO trunk deployment, OTDR test reports, and as-built diagrams delivered on handover.

Outcome

Deployment completed on schedule and passed the client's compliance audit on first review. Documentation package accepted without revision.

12
Racks deployed
0
Audit revisions
On time
Schedule variance